Assembled, Not Built: GB1 Reuses Barcelona Base for Naples 2027
As preparations continue for the 38th America’s Cup in Naples, GB1 is reassembling its team base using 90% of the structure previously used in Barcelona, reducing the need for new materials, construction waste and associated carbon emissions.
Preparations for the 38th America’s Cup are taking shape in Naples, including the reassembly of GB1’s team base ahead of racing in 2027.
But importantly, this is not a new building project. The base is being assembled, not built.
The modular facility was used by GB1 during the 37th America’s Cup in Barcelona in 2024 before being dismantled and transported to Naples. Now, 90% of the existing base is being reused and reassembled for the next America’s Cup campaign.
From Barcelona 2024 to Naples 2027
Following the 37th America’s Cup in Barcelona in 2024, GB1’s modular base was dismantled and transported to Naples. Now, 90% of the existing base is being reused and reassembled for the next America’s Cup campaign.
“Pretty much everything you see was used in Barcelona, so it’s really important for our sustainability credentials that we minimise our environmental footprint. The base was originally designed to be reused, packed up, transported and then built again here in Bagnoli,” said GB1 CEO Ian Walker.
That ability to reuse the base was considered from the outset. Rather than creating permanent infrastructure for a single event, the modular structure was designed to move with the team, extending the life of existing materials from one America’s Cup campaign to the next.
Reusing the existing structure means significantly less new material is required to establish the team’s home in Naples. In turn, that means less construction waste and lower associated carbon emissions. By reassembling the existing base instead of building a new equivalent structure, an estimated 400 tCO2e of emissions have been avoided.*
Reuse, relocate, reassemble
The modular nature of the base is central to this approach.
Rather than creating a permanent facility for a single event, the structure is designed to be dismantled, transported and reassembled. The same modules that formed GB1’s base in Barcelona can therefore become the team’s home once again in Naples.
The structure is also 100% removable, meaning that when it is no longer required, it can be dismantled without leaving a permanent building behind. This helps to limit the long-term impact on the surrounding area and environment.
Reducing our impact where we can
An America’s Cup campaign requires the movement of people, boats, equipment and infrastructure around the world. While that impact cannot be removed entirely, GB1 is focused on finding practical ways to minimise it wherever possible.
That approach extends beyond the reuse of the base itself. 40 solar panels are set to be installed on the Naples facility, providing a source of renewable electricity on site and helping to reduce the team’s reliance on grid electricity and associated fossil-fuel generation.
Together, these measures are about considering the full lifecycle of the infrastructure needed to support an America’s Cup campaign, from the materials used to assemble it to how it is powered and what happens when the campaign moves on.
From Barcelona 2024 to Naples 2027, the location may have changed, but much of the base has not.
90% reused. 100% removable. An estimated 400 tCO2e avoided. And 40 solar panels to be installed.*
*Estimated avoided emissions compared with building a new equivalent structure.